PM Surya Ghar Existing Solar Upgrade 2026
Calculate possible balance CFA, expand an old rooftop plant, decide whether modules, inverter, structure and meter can be reused, and keep the old subsidy, new equipment, DCR, portal, inspection, warranty and commissioning records consistent.
Last Updated: July 25, 2026
Existing Solar Upgrade Questions Covered Here
- Official pre-existing RTS rule
- Types of solar upgrades
- Interactive additional-CFA calculator
- Additional-CFA examples
- Previous subsidy and balance capacity
- Existing system without old CFA
- Relocation rule
- Pre-upgrade audit
- Should capacity be increased?
- Roof and structure reuse
- Old module compatibility
- DCR and ALMM verification
- Can the existing inverter be reused?
- When a new inverter is needed
- String and MPPT redesign
- Battery or hybrid upgrade
- Sanctioned load and phase
- Net-meter upgrade
- Documents checklist
- Application and approval process
- Registered vendor and agreement
- Installation and commissioning
- DISCOM inspection
- Warranty and CMC after expansion
- Upgrade cost and savings
- Correction, delay and rejection
- Upgrade scams and red flags
- Frequently asked questions
Official Rule for a Pre-Existing Rooftop Solar Plant
The residential CFA operational guideline states that a rooftop solar installation of a residential consumer or RWA that has availed CFA under a prior or current MNRE rooftop-solar scheme and subsequently increases the installation size is eligible for additional CFA only for the balance capacity up to three kW of the overall rooftop plant size.
Balance Capacity
Additional CFA can apply only to the supported capacity that remains below the overall three-kWp household ceiling.
Overall Plant Size
Old modules and new modules form one cumulative system for CFA-ceiling purposes.
Beyond 3 kWp
Additional household solar capacity beyond three kWp receives no additional Central CFA under the normal household slab.
Old CFA History
Preserve the earlier scheme, sanction, plant capacity and subsidy-release record.
New supported balance = remaining slab capacity between the old subsidised plant and the three-kWp overall household ceiling.
New total capacity may exceed three kWp, but the portion beyond three kWp does not receive additional household CFA.
Which Type of Upgrade Are You Planning?
| Upgrade | Does module capacity increase? | Possible additional CFA? | Main approval issue |
|---|---|---|---|
| Add new solar modules | Yes | Potentially, only for eligible balance up to 3 kWp overall | DCR, design, capacity, DISCOM and portal update |
| Replace damaged modules at the same total capacity | No | Normally no fresh CFA merely for replacement | Warranty, DCR, compatibility and serial update |
| Replace inverter only | No | No additional CFA based on inverter size | Phase, MPPT, technical specification and inspection record |
| Add a battery | No | No additional module-based CFA merely for battery | Hybrid approval, protection and metering |
| Convert on-grid to hybrid | Not necessarily | Only any separately added eligible module capacity may be relevant | Regulatory approval and reverse-power protection |
| Replace mounting structure | No | No fresh CFA merely for structure replacement | Structural safety and warranty |
| Move the old plant to a new house | No | No fresh CFA for the relocated system | New connection, metering and regulatory approval |
| Expand an RWA common plant | Yes | Subject to the RWA/GHS ceiling and earlier supported capacity | 500 kWp, 3 kWp per house, individual systems and common connection |
For society projects, use the PM Surya Ghar RWA subsidy guide .
Interactive Existing-Solar Additional CFA Calculator
This calculator estimates the current-slab CFA attributable to balance capacity up to three kWp overall. It is designed for a residential plant that already received MNRE CFA under a prior or current scheme. Final eligibility depends on the National Portal, earlier sanction record, current guideline, compliant installation and DISCOM verification.
Additional CFA Examples for Existing Solar
| Old subsidised plant | Total after upgrade | Supported added capacity | Estimated ordinary-State additional CFA |
|---|---|---|---|
| 1 kWp | 2 kWp | 1 kWp | ₹30,000 |
| 1 kWp | 3 kWp | 2 kWp | ₹48,000 |
| 1 kWp | 4 kWp | 2 kWp | ₹48,000 |
| 1.5 kWp | 3 kWp | 1.5 kWp | Estimated current-slab difference: ₹33,000 |
| 2 kWp | 5 kWp | 1 kWp | ₹18,000 |
| 2.5 kWp | 4 kWp | 0.5 kWp | ₹9,000 |
| 3 kWp or more | Any higher total | 0 kWp under normal household CFA ceiling | ₹0 additional Central CFA |
How Previous Subsidy Affects the New CFA Claim
Preserve the earlier plant and subsidy history even when the old CFA rate was lower. In the guideline example, a one-kW Phase II system that received ₹14,588 and later expands to four kW receives ₹48,000 on the supported two-kW balance. The example does not provide another three-kW full subsidy merely because the earlier amount was lower.
- Old scheme or programme name
- Old application and sanction number
- Old installed DC capacity
- Old subsidy amount and payment date
- Old module and inverter records
- Existing meter and commissioning date
- New added module capacity
- New total cumulative plant capacity
- Balance supported capacity up to three kWp overall
What If the Existing Solar Plant Never Received CFA?
The explicit pre-existing-RTS clause describes a plant that already availed CFA under a prior or current MNRE scheme. It does not state a universal automatic CFA method for every privately installed or unregistered old system that never received subsidy. An already completed plant may also predate the required National Portal application, registered-vendor and inspection workflow.
- Record when and how the old plant was installed.
- Check whether it was approved by the DISCOM and linked to the same consumer connection.
- Check whether any Central or State subsidy was received.
- Check module DCR, model and serial records.
- Ask the National Portal or DISCOM how the base capacity will be recorded.
- Obtain written confirmation of eligible added capacity before ordering modules.
- Do not use the calculator as proof of entitlement when no prior CFA record exists.
Relocation Does Not Create Fresh CFA
The operational guideline states that a rooftop solar installation is eligible for CFA only once after installation. When an already installed system is shifted or relocated to a new location, the relocated system is not eligible for CFA under the scheme.
Moving to a New House
The old subsidised plant does not become a new subsidised installation.
Moving Between Roof Sections
May need structural, electrical and DISCOM review, but does not create fresh CFA.
Adding New Modules
Only eligible balance added capacity may be considered; the relocated old modules remain old capacity.
Consumer Connection Change
Requires written DISCOM and portal guidance; do not assume subsidy history disappears.
Complete an Existing-System Audit Before Buying Anything
- Confirm old physical module quantity and wattage.
- Confirm old total DC capacity.
- Confirm inverter model, AC rating, phase and unused input capacity.
- Export at least 12 months of generation data.
- Check old module output and visible defects.
- Test insulation, polarity, earthing and protection through qualified personnel.
- Check roof leakage and structural corrosion.
- Check current sanctioned load, meter and billing mechanism.
- Check remaining OEM and CMC warranties.
- Identify all documents missing from the old project.
Assess maintenance history with the rooftop solar maintenance and warranty guide .
Should You Increase Solar Capacity?
More capacity is not automatically better. Compare the old system’s actual generation with present consumption, daytime load, export credit, roof area, tariff and future appliances such as an EV, heat pump or air conditioner.
| Question | Evidence | Upgrade implication |
|---|---|---|
| Is the old plant under-performing? | Normalised generation, alarms and tests | Repair first; expansion may hide an unresolved fault |
| Has annual consumption increased? | 12–24 months of bills | Added capacity may reduce new daytime imports |
| Is export compensation attractive? | Current State billing regulation | Oversizing economics depend on export value |
| Is suitable roof area available? | Shade and layout survey | New modules need unshaded, maintainable space |
| Will the inverter accept more modules? | Datasheet and string calculation | May avoid or require inverter replacement |
| Will load or phase change? | DISCOM consumer record and design | May require connection, meter or protection work |
Estimate the right total capacity through the home solar system-size guide and value through the PM Surya Ghar savings calculator .
Can the Old Mounting Structure Be Reused?
Reuse is possible only after a structural and condition audit. Newer modules may differ in length, width, frame thickness, clamp zone, weight and wind loading.
- Member dimensions and material grade
- Foundation, anchor, ballast and roof interface
- Corrosion and coating loss
- Loose fasteners and weld quality
- Original wind design and new module dimensions
- Clamp position and manufacturer requirements
- Drainage, waterproofing and maintenance access
- Added row wind interaction and shading
- Remaining design life
- Responsibility and warranty after modification
Review usable space using the solar-panel rooftop-area guide .
Can Old and New Solar Modules Work Together?
Separate MPPT or Inverter
Old and new module groups can often be electrically separated when the design and equipment permit it.
Mixed in One Series String
Different current, voltage, degradation and characteristics can reduce output or violate design limits.
Same Model, Different Age
Ageing and batch characteristics still require current and voltage review.
Replacement Module
Record electrical compatibility, physical dimensions, DCR, serial and warranty.
- Open-circuit voltage and temperature correction
- Maximum-power voltage
- Short-circuit and operating current
- Module degradation and condition
- Bypass-diode and connector compatibility
- String module count
- MPPT operating window
- Maximum inverter input current
- Roof orientation and shade pattern
DCR and ALMM Checks for the Expanded Plant
The guideline says modules used in the installation must be domestically manufactured from domestically manufactured cells and that use of non-DCR modules in any form makes the installation ineligible for CFA. For an expansion, verify the old and new module records and obtain written portal or DISCOM guidance if an old section creates uncertainty.
- Old module manufacturer, model and serial register
- Old DCR or prior-scheme compliance record
- New module domestic-cell and domestic-module evidence
- Current applicable ALMM module and cell records
- New invoice and delivery batch
- No undocumented module substitution
- Physical label, portal, PCR and invoice consistency
Use the PM Surya Ghar DCR module verification guide .
Can the Existing Solar Inverter Be Reused?
An inverter can be reused when the expanded module design remains within every manufacturer limit and the unit meets current scheme and DISCOM requirements.
| Inverter check | Why it matters |
|---|---|
| Maximum DC voltage | New series strings must remain safe during the coldest expected condition |
| MPPT voltage range | Each string must operate inside the tracking window |
| Maximum input current | Parallel or high-current modules can exceed input limits |
| Number of MPPTs | Old and new orientations or module groups may need separation |
| Allowed DC oversizing | Manufacturer design limit controls permissible module-to-inverter ratio |
| AC rating and phase | Must match connection and approved interconnection |
| Age and warranty | Expansion can increase reliance on an older electronic component |
| Firmware and monitoring | New strings and limits may require configuration and data updates |
| Grid and protection compliance | DISCOM inspection includes technical and anti-islanding requirements |
Follow the solar-inverter selection guide .
When Should the Inverter Be Replaced?
- The old inverter cannot accept the new DC voltage or current.
- There are not enough independent MPPT inputs.
- The old unit has repeated faults or poor service support.
- The connection changes from single phase to three phase.
- The planned battery requires a compatible hybrid architecture.
- The old inverter lacks required protection or certification.
- Monitoring and data cannot distinguish old and new arrays.
- Expected clipping or derating makes reuse uneconomic.
One New Larger Inverter
Can simplify monitoring but may require rewiring and changes to old strings.
Second Independent Inverter
Can separate old and new modules but needs AC, protection, meter and approval review.
Microinverter or Optimiser Addition
May help complex roofs but must fit scheme, safety and DISCOM requirements.
Cheap Unverified Replacement
Can create phase, protection, warranty and inspection failure.
Redesign Strings and MPPTs for the Expansion
Number of modules in series × temperature-corrected module Voc must remain below the inverter’s maximum permitted DC input voltage.
MPPT check:
Expected operating string voltage should remain inside the MPPT range across site temperatures.
- Keep different orientations on separate MPPTs where practical.
- Avoid mixing materially different operating currents in one series string.
- Check parallel-string current and input connector limits.
- Use matched approved connectors; avoid improvised connector pairs.
- Update string labels, layout and single-line diagram.
- Retest polarity, insulation and open-circuit voltage.
- Record MPPT values at commissioning.
Adding Battery Storage or Converting to Hybrid
The guideline allows additional technology components such as battery storage, but CFA calculation remains based on eligible solar-module capacity. Grid-connected behind-the-meter or hybrid systems are subject to approval by the respective Electricity Regulatory Commission and DISCOM inspection of reverse-power protection. Fully off-grid installations are not eligible for CFA.
- Confirm the State regulator permits the proposed configuration.
- Confirm whether the existing inverter can support battery operation.
- Separate backed-up circuits from non-backed-up high loads.
- Check battery chemistry, usable capacity, cycle life and warranty.
- Check fire safety, ventilation and enclosure location.
- Check reverse-power relay or zero-export settings where required.
- Update SLD, protection and portal records.
- Do not describe standard on-grid solar as outage backup.
Compare configurations using the on-grid, hybrid and off-grid guide .
Sanctioned Load, Connection Phase and Feasibility
An expansion changes cumulative generation capacity and may require a new or updated utility record even when the old plant was approved. Current scheme measures simplify rooftop approval and provide automatic load enhancement up to 10 kW, but the live DISCOM workflow, phase and metering still must be correct.
- Old approved solar capacity
- New proposed total capacity
- Current sanctioned load or contract demand
- Single- or three-phase connection
- Existing and proposed inverter phase
- Service cable and distribution board capacity
- Transformer or local interconnection condition
- Updated feasibility or auto-load record
Use the PM Surya Ghar feasibility and load guide .
Does the Existing Net Meter Need Replacement?
The current meter may remain suitable, require reprogramming or need replacement, depending on phase, current rating, approved metering arrangement, cumulative capacity and State/DISCOM specifications.
| Meter question | Upgrade check |
|---|---|
| Is the meter already bidirectional? | Confirm import/export registers and approved use |
| Does the phase change? | A new phase-compatible meter and agreement may be needed |
| Is the rating sufficient? | Check service, meter and CT requirements for the new total capacity |
| Does the settlement mechanism change? | Confirm net metering, net billing or another State-approved arrangement |
| Is smart-meter integration required? | Check AMISP and current DISCOM process |
| Is the old agreement capacity-specific? | Execute an amendment or new agreement when required |
Follow the PM Surya Ghar net-meter process guide .
Documents Required for an Existing-Solar Upgrade
Old Project Records
- Old application and sanction
- Old CFA-release proof
- Invoice and commissioning
- Old module/inverter serials
- Meter and agreement
New Design Records
- Load and generation audit
- New total capacity
- Roof layout and SLD
- String and MPPT calculation
- Structure audit
New Equipment Records
- DCR module evidence
- New serial register
- Inverter and protection
- Warranty documents
- Delivery and invoice
Portal and DISCOM Records
- New application or upgrade ID
- Capacity approval
- Geo-tagged photographs
- PCR and tests
- Inspection and meter update
CFA Records
- Old subsidised capacity
- Balance capacity sheet
- Applicable rate category
- Updated token amount
- Bank or loan account
Handover Records
- Old/new component map
- Updated monitoring
- Warranty allocation
- CMC responsibility
- Final test report
Organise the file with the PM Surya Ghar documents checklist .
Existing Solar Upgrade Application Process
- Collect the old application, subsidy, commissioning and equipment records.
- Confirm the old subsidised DC capacity and current consumer connection.
- Audit generation, roof, structure, inverter, strings, meter and protection.
- Calculate the required new total capacity and possible CFA balance.
- Check the current National Portal workflow for pre-existing RTS or capacity enhancement.
- Confirm feasibility, load, phase and meter treatment with the DISCOM.
- Select a registered vendor and freeze a compliant technical design.
- Verify DCR and current applicable module/cell records before purchase.
- Install and test the added system without compromising the old plant.
- Update actual cumulative capacity, modules, inverter and photographs in the portal.
- Complete DISCOM inspection, metering and commissioning updates.
- Verify the e-token or eligible CFA amount reflects only supported balance capacity.
- Preserve old and new warranties, serial maps, monitoring and CMC records.
Review registration in the PM Surya Ghar online application guide and track progress with the application-status guide .
Select a Registered Vendor Experienced in Expansion Work
- Current National Portal registration
- Experience with brownfield or existing-plant expansion
- Written audit of old equipment
- Clear separation of old and new work
- Exact DCR modules and inverter design
- String and MPPT calculations
- Structure and roof responsibility
- Portal and DISCOM capacity-update support
- Warranty treatment of inherited equipment
- Five-year CMC for the new work and complete-system responsibility
- Itemised price and milestone payments
Compare companies through the PM Surya Ghar registered-vendor guide .
“The Vendor shall audit the pre-existing rooftop solar system identified in Schedule A, verify its capacity, modules, inverter, strings, structure, protection, meter and available records, and state which existing components it accepts for integration. The Vendor shall design and install the added capacity listed in Schedule B, ensure DCR and technical compliance, update cumulative plant documents, assist with National Portal and DISCOM processes and identify warranty and CMC responsibility separately for old and new components.”
Installation-Day Rules for a Solar Expansion
- Record the old system’s final pre-work generation and alarms.
- Photograph old module and inverter serials.
- Use a documented shutdown and isolation process.
- Protect old modules, cables and roof waterproofing.
- Keep old and new component batches identifiable.
- Use approved matched connectors and cable.
- Update structure and wind calculations.
- Label new strings, isolators and protection.
- Retest the whole cumulative system.
- Update monitoring capacity and ownership.
- Capture geo-tagged completion photographs.
Follow the PM Surya Ghar solar-installation process guide .
What the DISCOM May Verify After Expansion
- Consumer account and old approved plant
- Old and new cumulative module DC capacity
- Prior subsidy and eligible balance capacity
- DCR compliance and all module serials
- Inverter model, rating, phase and MPPT design
- Structure, cabling, isolation and labels
- Earthing, surge and anti-islanding protection
- Updated meter and agreement
- Invoice, PCR, SLD, tests and photographs
- Portal and physical-plant consistency
Prepare with the PM Surya Ghar DISCOM inspection guide .
Warranty and CMC After Capacity Expansion
Old and new components can have different warranty dates. The new vendor must define whether it accepts responsibility only for the added work or for the integrated system. Under the scheme, registered vendors provide five years of free repair and maintenance from commissioning for their covered installation, but the expansion’s commissioning and responsibility should be written clearly.
| Component or work | Warranty question |
|---|---|
| Old modules | Original product and performance warranty, remaining term and valid claim route |
| New modules | New invoice, serials and product/performance warranty |
| Old inverter reused | Does added DC loading affect warranty or service? |
| New inverter | Product warranty, labour, transport and commissioning date |
| Modified structure | Who warrants old and new structural members and roof interface? |
| Integrated electrical work | Who owns faults at the old-new connection boundary? |
| Five-year CMC | Does the vendor cover only added capacity or the whole expanded system? |
Calculate Upgrade Cost and Savings Correctly
An expansion can cost more per added kWp than a new clean installation because it may require audit, rewiring, structure modification, phase conversion, meter work or inverter replacement. Compare the net cost after only the eligible balance CFA.
New modules + inverter/structure/electrical/meter work + taxes and fees − eligible additional CFA − applicable State support
Annual added benefit:
Additional generation × self-consumption value + export credit − added maintenance and financing cost
- Separate essential repair from optional expansion cost.
- Do not apply CFA to capacity above the supported balance.
- Include the cost of new inverter only when technically necessary.
- Include roof restoration and meter work.
- Use the current household tariff and export credit.
- Include downtime during modification.
- Include post-CMC maintenance and future inverter reserve.
Compare household scale through the 1kW , 2kW and 3kW cost guides .
Where finance is needed, review the PM Surya Ghar solar-loan guide and track CFA using the subsidy-payment status guide .
Correction, Approval Delay or Rejection During an Upgrade
Wrong Old Capacity
Correct the old subsidy and commissioning record before CFA calculation.
Wrong New Total
Recalculate physical module wattage × quantity and update every record.
DCR or Equipment Failure
Correct the physical system, not only the portal text.
Token Amount Dispute
Attach old CFA, cumulative capacity, inspection and slab calculation evidence.
Use the application-correction guide , approval-delay guide and rejected-application guide .
If a new installer must take over, follow the PM Surya Ghar change-vendor guide .
Existing-Solar Upgrade Scams and Red Flags
Fresh ₹78,000 Guarantee
An agent promises the full household CFA again without counting the old subsidised plant.
Relocation as New Installation
Old modules are moved and invoiced as a fresh subsidised plant.
Inverter-Based Subsidy Claim
A larger inverter is presented as additional solar capacity.
Non-DCR Old-New Mix
The consumer is told that only the new row needs to satisfy DCR.
Hidden String Overload
New modules are connected without voltage and current calculations.
Duplicate Application
A second claim is created instead of declaring the existing plant and earlier CFA.
- Use the consumer’s own official login.
- Verify the old subsidy history before signing.
- Demand the cumulative capacity calculation.
- Verify DCR, module and inverter models physically.
- Keep OTP, password and bank credentials private.
- Report suspected false invoices, forged labels or bribery to appropriate authorities.
Frequently Asked Questions
Can I get PM Surya Ghar subsidy if I already have solar?
When the old residential or RWA plant received MNRE CFA and you expand it, the guideline allows additional CFA only for the balance supported capacity up to three kWp of overall household plant size.
I have a subsidised 1 kW system and want a total 4 kW. How much additional CFA?
The official ordinary-State example provides additional CFA on two kW only, amounting to ₹48,000.
Why is only 2 kW supported when I add 3 kW?
The old one kW plus two supported new kW reaches the three-kWp overall household CFA ceiling. The remaining added one kW gets no additional Central CFA.
Does the old subsidy amount get subtracted from ₹78,000?
Follow the official pre-existing-RTS calculation and portal result. The guideline’s Phase II example gives ₹48,000 for the supported two-kW balance even though the old one-kW subsidy was ₹14,588.
Can I get additional CFA after my total plant already reached 3 kWp?
No additional household Central CFA is provided beyond the overall three-kWp supported ceiling.
Can I install more than 3 kWp?
Yes, subject to technical, DISCOM and metering approval, but the capacity beyond three kWp does not receive additional normal household CFA.
Does replacing an inverter qualify for subsidy?
No additional CFA is calculated merely from inverter replacement or size. CFA is based on eligible module DC capacity.
Does adding a battery qualify for extra CFA?
The battery itself does not increase the module-based CFA. The hybrid arrangement must also meet regulatory and DISCOM requirements.
Can I relocate my old subsidised solar and claim again?
No. The guideline states that a relocated already installed system is not eligible for fresh CFA.
Can I reuse my old inverter?
Yes, only when voltage, current, MPPT, DC oversizing, phase, protection, age and warranty checks all support the new design.
Can old and new modules share one string?
Only after engineering verification of voltage, current, degradation and compatibility. Separate MPPTs or inverters are often safer for different module groups.
Must new expansion modules be DCR?
Yes. The CFA guideline requires domestically manufactured modules made from domestically manufactured cells.
What if my old modules are not DCR?
Obtain written portal and DISCOM guidance before ordering an expansion. The current guideline says non-DCR modules in any form in the installation render it ineligible for CFA.
Does the old net meter automatically support the expansion?
Not always. Phase, current rating, cumulative capacity, agreement and State metering rules must be checked.
Do I need a registered vendor?
Yes, a consumer claiming CFA must use a vendor registered on the National Portal.
Will the DISCOM inspect the old modules too?
The DISCOM physically verifies the system presented for CFA. Keep old and new capacity, equipment and records available.
Can I expand an old system that never received subsidy?
Technical expansion may be possible, but the guideline does not provide one automatic CFA method for every old unsubsidised installation. Obtain written portal/DISCOM confirmation.
Does replacing old modules at the same capacity create fresh CFA?
No fresh CFA should be assumed merely for replacement. Use warranty and replacement-record procedures.
What documents prove my old subsidy?
Old application, sanction, capacity, invoice, commissioning, CFA-release record, meter and module/inverter serials.
Can I change vendor for the expansion?
Yes, choose a registered vendor, but clearly allocate responsibility for inherited equipment, integrated testing, warranty and CMC.
What if the token amount does not show the correct balance CFA?
Compare old subsidised capacity, new cumulative capacity, applicable rate and final inspection record, then raise a tracked grievance.
Does a larger new inverter increase subsidy?
No. Inverter capacity does not determine CFA; eligible module DC capacity does.
Should I repair the old plant before expansion?
Yes. Identify under-performance, alarms, insulation, earthing, structure and roof defects so the new capacity does not hide old problems.
Upgrade One Cumulative System, Not Two Unrelated Plants
A safe expansion connects the old scheme history and new work into one consistent record: consumer account, old CFA, old capacity, new added capacity, cumulative modules, inverter, strings, structure, meter, invoice, inspection, token, warranty and maintenance. Calculate the supported balance before ordering equipment.
Begin with the complete PM Surya Ghar guide and verify the upgrade’s general eligibility using the eligibility guide .
Official Sources
- PM Surya Ghar Muft Bijli Yojana National Portal
- Official Consumer Login and Application Portal
- MNRE Residential CFA Operational Guidelines
- MNRE Approved List of Models and Manufacturers
- Updated ALMM List-I for Solar PV Modules, 6 July 2026
- 8th Revision of ALMM List-II for Solar PV Cells, 22 July 2026
- PIB March 2026 PM Surya Ghar Process Update
Disclaimer
Wikisia is an independent informational website and is not affiliated with MNRE, PM Surya Ghar, REC, any DISCOM, vendor, bank, lender, module manufacturer, inverter manufacturer or State regulator.
Existing-system data, old subsidy records, upgrade fields, DCR treatment, capacity calculation, metering, State regulations and component-reuse acceptance can differ by project and live portal workflow. The calculator uses the current household CFA slabs and the guideline’s balance-capacity principle for planning. It is not an official sanction, electrical design, structural certificate, legal advice or guaranteed CFA. Obtain written confirmation before purchasing equipment.